Back to top

Hillcrest Storage Tank Replacement

Durable design, less susceptibility to leaks

To maintain safety at the Hillcrest water storage facility and improve its reliability, Denver Water is making major upgrades through work estimated to run through early 2020.

hillcrest tank replacement
Print

Tale of 3 Tanks

45 million

gallons total water storage

1,500

cubic yards of concrete per tank foundation

310

foundation's diameter in feet

39.643248, -104.9154762

Why it’s important

Denver Water developed the Hillcrest water storage facility in the early 1960s to replace several small, temporary pumping stations and improve the ability to reliably serve the burgeoning population of southeast Denver. Since then, the area’s population has continued to grow, placing increasing demand on the storage and pumping facilities on top of the wear and tear expected to come with age.

The major upgrades this project brings to the Hillcrest facility are an important part of Denver Water’s plan for continued reliable water service to the southeast Denver area.

How it affects our customers

We have made some great progress on-site over the past couple weeks. Please see the updates below as a reminder for what to expect over the next couple months, including concrete placements this fall. 

Construction update: Nov. 29, 2017

    Work activities at Hillcrest site

    Concrete Placement

    Floor of Tank 2

    The floor of Tank 2 is scheduled to be placed Saturday, Dec. 2. Like the other placements, there is a chance the schedule may change due to weather or other project timelines. Notice will be provided if the schedule changes.

    These placements will be similar to what neighbors experienced during the Tank 1 and 3 floor placements, and the roof of Tank 1 placement.

    Speed bumps

    In an effort to manage driver speeds through the construction site, speed bumps will be placed on the road that runs along Canyon Club Condominiums and exits at the east gate.

    Hillcrest tank map

    Construction hours at Hillcrest site

    General work hours (outside of weekend concrete placements) are 7 a.m. to 6 p.m., Monday through Friday. Saturday work (with the same hours) will continue to be an option that our contractor, MWHC, will use when necessary to keep the project on schedule or when the work could condense the overall timeline.

    Anticipated timeline

    • Tank replacement phase, mid-2016 through late 2019: Crews are replacing the two 15-million-gallon rectangular storage tanks with three same-sized, circular post-tensioned concrete tanks — a durable design less susceptible to leaks. The new tanks will sit slightly south of the existing tanks and will be buried up to roof height, which will be visible.
    • Pumping station replacement phase, 2018 through early 2020: Crews will replace the pumping equipment, which is outdated, and the pumping station's building.

    Contact

    Katie Knoll, Denver Water Public Affairs, 303-628-6117

    Katy Perrino, MWHC PR and Communications, 720-984-4011

    Neighbors: Join Nextdoor.com

    Videos

    Concrete floor pours: Tank 1 and Tank 2

    Denver7 on-site report and article, Aug. 24, 2016

    Read more

    Good Neighbor Commitment

    Fact Book and Community Commitment (PDF)

    Upgraded storage for the water down below