Big milestone for Denver Water’s Gross Reservoir Expansion Project

New concrete reaches height of existing structure as dam officially starts to go up.

Over the past year, Gross Dam in Boulder County has been getting wider and thicker. Now, it’s finally getting taller.

At the end of June, construction work, which began at the base of the dam, reached an elevation of 7,289 feet above sea level — the height of the crest of the original dam.

The work is all part of the Gross Reservoir Expansion Project, which will raise Gross Dam by 131 feet.

The project is designed to nearly triple the physical water storage capacity of the reservoir, which would add balance and resiliency to Denver Water’s collection system.

Denver Water collects melted snow and rain from the mountains and stores it in reservoirs, which are used to supply water to 1.5 million people in the Denver metro area.

Gross Dam on June 24, 2025, at the point where the expansion work reached the top of the existing dam. You can see the new spillway walls in the center of the dam. Photo credit: Denver Water.

“It’s taken a lot of work by a lot of dedicated people to reach this point, so this is a huge milestone for them and this project,” said Jeff Martin, Denver Water’s program manager for the Gross Reservoir Expansion Project.

Before the dam could be raised, workers spent two years preparing the existing dam and excavating the canyon walls for the new concrete that will go on top of the old concrete.

In 2024, crews began building new concrete “steps” that started at the bottom of the original dam and now rise 340 feet from the valley floor.

A bulldozer spreads a load of roller-compacted concrete across the top of Gross Dam. Photo credit: Denver Water.

Each 4-foot step is made of several layers of roller-compacted concrete that is placed on top of the existing structure. Traditional concrete is used on the exterior face of the dam as it holds up better to the elements.

“It’s been impressive to watch this work on the dam,” said Casey Dick, Denver Water’s deputy program manager for the Gross Reservoir Expansion Project. “Now that we’ve reached the crest, we’ll say goodbye to the old dam as it will be covered up with new concrete and we’ll start the process of making the dam taller.”

A worker guides a load of concrete into a truck before placement on the dam. Photo credit: Denver Water.

Lots of concrete

Raising Gross Dam requires a large amount of concrete. To reach the crest of the original dam, engineers say they used 400,000 cubic yards of concrete, which is about half of the total amount of concrete needed for the entire project. Work to build the additional 131 feet will require another 400,000 cubic yards of concrete.

This means the top one-third of the project requires the same amount of concrete as the bottom two-thirds according to Martin. This is because the dam will be much wider as it goes up. In fact, the new dam will be nearly twice as wide going from 1,050 feet across the crest of the old dam, to 2,040 feet across the new crest.

The top of the dam at the end of June shows the finished steps and spillway walls on the face of the dam on the left; the types of vehicles used; and the concrete batching plant in the background. Photo credit: Denver Water.

Prepping the crest

Before concrete could be placed on top of the crest of the original dam, crews had to prepare the crest’s surface by removing the top 12” of concrete.

Workers are tethered to the dam as they use a saw to “score” the top of the dam to prepare it for new concrete. Photo credit: Denver Water.

The three-step process started with a large circular saw, which “scored” the top of the crest. Then, an excavator used a hydraulic chisel to chip away at the concrete and remove 9 inches of concrete. The final step involved hydroblasting the concrete, which removed another 3 inches of concrete.

“We had to do the demolition work on top to roughen up the surface, which ensures a solid bond when we place the new concrete on top,” Dick said. “By doing this prep work, the old and new concrete will form a cohesive joint so the two materials function as one structure.”

An excavator chips away and removes concrete after the scoring process. Photo credit: Denver Water.

New spillway

Workers are also building two new spillway “training” walls. These 18-foot-tall walls stick out of the dam like fins and stretch from the bottom to the top.

Workers build the new spillway “training” walls on the face of the dam in February. Photo credit: Denver Water.

The purpose of a spillway is to channel water down the face of a dam in the event the reservoir behind it reaches capacity. These safety features also protect dams during flooding situations.

Watch a video of the work to prepare the crest for new concrete and the construction of the training walls.

What’s next

Martin says workers will continue building the concrete steps this summer and fall with the goal of reaching the dam’s new height of 471 feet by the end of 2025. Completion of the project is expected in 2027.

Casey Dick, deputy program manager for the Gross Reservoir Expansion Project, shows off the old crest of the dam on the right and the new addition to the dam on the left. Photo credit: Denver Water.

“We want to say thank you to all the men and women working on this project and celebrate this milestone of reaching the crest,” Martin said. “We look forward to the next couple of months of building the new dam and securing the water future for our Denver Water customers.”