Major milestone for Gross Dam construction
In the early morning hours of Wednesday, June 3, 2026, construction crews reached a major milestone on Denver Water’s Gross Reservoir Expansion Project: completion of the dam-raising phase.
Workers placed the final layer of roller-compacted concrete at 3 a.m., raising the dam’s height to 470 feet above the valley floor.
In the coming months, crews will place one last foot of concrete on top of the roller-compacted concrete to raise the dam to its fully completed new height of 471 feet tall.
But the major work to raise the dam — a project designed to nearly triple the water storage capacity of Gross Reservoir and add balance and resiliency to Denver Water’s system that supports 1.5 million people — is done.
In all, it took nearly 800,000 cubic yards of both roller-compacted and conventional concrete to raise the dam. To put that in perspective, it only took 29,000 cubic yards of concrete to build Empower Field at Mile High in Denver.
The final 21 feet of roller-compacted concrete was built in two sections with a 160-foot gap in the middle of the dam for the new spillway. You can learn about that process in this video.
Dam raising construction began in the spring of 2024.
Remaining work on the dam is expected to take another year and includes adding a final foot of conventional concrete on the crest that will serve as a protective layer designed to withstand the elements better than the roller-compacted concrete.
Other work on the dam over the next year includes building safety walls on the top, building the spillway crest, constructing a bridge over the spillway gap, and completing the stilling basin on the bottom of the dam.
“We’re incredibly excited and proud to have reached this milestone,” said Jeff Martin, Denver Water’s program manager for the Gross Reservoir Expansion Project. “Our crews have done an exceptional job building a high-quality dam that was designed to help provide water security for our customers for years to come.”