Q&A on the Gross Reservoir Expansion Project

Denver Water’s program manager talks milestones and water security.

Completion of the dam-raising phase of the Gross Reservoir Expansion Project in Boulder County marks a significant engineering feat for Denver Water, one that highlights the utility’s ongoing work to ensure water security for 1.5 million people in Denver and surrounding suburbs.

As Denver Water marks the construction milestone, Jeff Martin, the program manager for the Gross Reservoir Expansion Project, gave an update on the work and discussed the benefits of the project designed to nearly triple the storage capacity of Gross Reservoir.

What milestone for the Gross Reservoir Expansion Project occurred in June?

Raising Gross Dam is an incredible engineering and construction feat that Denver Water has been pursuing for over 20 years. On June 3, 2026, Denver Water marked a major milestone by topping out the roller-compacted concrete portion of the expansion project, raising the dam 470 vertical feet from the valley floor to the top, 130 feet higher than the old dam.

Image
A wide view
Gross Dam on June 2, on the final day of roller-compacted concrete work. The dam is now 130 feet taller than the original structure. A final foot of concrete will be placed on top over the coming months to reach the final height of 471 feet. Photo credit: Denver Water.

What work is still left to do?

Denver Water has about a year and a half worth of work to complete the dam-construction phase of the expansion project. The remaining work includes adding 1 foot of protective, conventional concrete to the top of the roller-compacted concrete, installing a water gate, completing the spillway crest, building a bridge over the spillway itself, and finishing the stilling basin at the bottom.

What is the benefit of a larger reservoir for Denver Water?

The new reservoir is designed to boost Denver Water’s overall water storage capacity by 11%. The expanded reservoir is capable of holding an additional 25 billion gallons of water.

This project provides water security and reliability for 1.5 million people around Denver and our surrounding communities by nearly tripling the size of Gross Reservoir behind the new dam.

The northern part of Denver Water’s collection system needs more water storage because of an imbalance in its water storage system. Ninety percent of the utility’s water is stored on the south side of the collection system, while just 10% is stored on the north end. This project will help balance that by allowing Denver Water to store more water on the north side, which will help provide a secure water future to Denver.

Image
A graphic that shows Denver's water storage imbalance. 90% of water is on the south side; 10% is on the north.
Denver Water has a water storage imbalance, with 90% of its storage on the south side of its collection system and only 10% on the northern side. Expanding Gross Reservoir will add more balance to the overall water storage system. Image credit: Denver Water.

How would a larger reservoir help during droughts?

Denver Water is coming off one of the worst snowpacks on record and one of the most memorable droughts in over 20 years. This project is a critical part of how Denver Water will manage through future droughts. The expanded reservoir will allow more water to be stored in our system, when it’s available, for use when it’s needed. This new storage will provide flexibility and resilience for how we collect, treat and deliver water to customers.

Image
An aerial view of Gross Reservoir in 2002, when water levels were dangerously low.
Gross Reservoir on Nov. 13, 2002. During Colorado’s last major drought in 2002-03, water levels in Gross Reservoir dropped to 32% of capacity, meaning the utility’s northern collection system was dangerously close to running out of water. An expanded reservoir will be capable of storing more water, collected during wet years, and used to get through times of drought. Photo credit: Denver Water.

How does the project help Denver Water prepare for the impacts surrounding climate change?

As Denver Water plans for the uncertainty of climate change, including more variability and extremes in weather patterns, a bigger bucket allows us to capture and store more water, which provides more flexibility. In really wet years, Denver Water can capture more water to offset dry years. The bigger reservoir allows us the flexibility to maneuver and work with our changing climate.

How has Denver Water addressed the environmental impacts of the expansion project?

Denver Water worked with stakeholders on the West and East slopes of the Continental Divide to identify ways to make this project a net environmental benefit.

Over the 20-year process of permitting and building Gross Dam, we’ve made major commitments to provide environmental enhancements and mitigation for this project, including committing $30 million to over 60 different environmental enhancement projects to offset impacts of the Gross Reservoir Expansion Project.

One of the goals of expanding Gross Reservoir was to improve stream health on some of the streams the project touches, including stream restorations on the Williams Fork and Fraser rivers in Grand County and South Boulder Creek in Boulder County.

Image
A small creek lined by rocks and shrubs.
Denver Water completed a stream restoration project on South Boulder Creek in Boulder County in 2019. Photo credit: Denver Water.

Denver Water also set aside ecologically sensitive fens and wetlands to compensate for the wetlands that were disturbed during the project.

Image
A field of golden-green marshy grasses with mountains in the background.
Restoration of the Fourmile Fen on Denver Water property in Park County is an example of an environmental mitigation effort. Photo credit: Denver Water.

Are there still legal issues surrounding the project?

As of July 2026, the Gross Reservoir Expansion Project is still the subject of ongoing litigation in the 10th Circuit Court of Appeals. Denver Water is confident the project will move through those challenges, and we'll see an expanded reservoir in the future. The timing for when we'll fill the expanded reservoir to its new, larger capacity will depend on the resolution of current litigation in federal courts, as well as water availability once the project is complete.